Once finished, the greenway will be linked to the East Bay Bike Path, for an additional 14.5 miles (23.3km) of trail to Bristol, Rhode Island. The Blackstone River Greenway is also a designated section of the East Coast Greenway, the 3,000-mile trail system connecting cities from Maine to Florida.
History
In 1985, the Blackstone River Valley National Heritage Corridor (known after 1999 as the John H. Chafee Blackstone River Valley National Heritage Corridor) was designated by the United States Congress, following the path of the Blackstone River from Providence to Worcester.
Rhode Island
In 1997, the Rhode Island Department of Environmental Management and Department of Transportation began work on the first Rhode Island segment, from Lincoln to Ashton.[2] This segment was completed in 1998. A second Rhode Island segment was completed in 2002, from Ashton to Manville.[3] In August 2007, a bridge reconstruction project at Martin Street in Lincoln was completed, ending a three-year bike path closure. The new bridge incorporated a major safety improvement with the path passing underneath Martin Street instead of meeting it at grade.[4] In November 2007, a 2-mile (3.2km) extension from Manville to the Woonsocket Water Treatment Plant was opened. A 1-mile (1.6km) segment from Lonsdale to Valley Falls, which includes more than 500 feet (150m) of boardwalk over part of the Lonsdale Marsh, opened in 2008. A segment through the River's Edge Recreational Complex in Woonsocket was completed in 2008, and that segment was linked to the previously-completed portions to the south later that year. In 2011, an 8.5 miles (13.7km) segment of on-road bicycle lanes opened connecting the Blackstone River Greenway with the East Bay Bike Path, starting in Providence. In 2013, sharrows were painted through Woonsocket from the Massachusetts border to the River's Edge Recreational Complex.[5]
In early Summer 2017, a new 0.6 miles (0.97km) section of path was completed along the Seekonk River in Providence, stretching from Gano Street to Pitman Street, which was extended by a further 0.2 miles (0.32km) in 2020. A $4.5 million section of path in Woonsocket known as Segment 8C was completed in 2019, consisting of 0.6 miles (0.97km) of path from the Massachusetts border to Cold Spring Park in Woonsocket including a 182-foot truss bridge over the Blackstone River.[6] Segment 8B1, a further 0.6 miles (0.97km) of path along Truman Drive in Woonsocket, was opened in 2020. As of 2021 the total Rhode Island portion of the greenway is 12 miles (19km) long, 10 miles (16km) of which make up the longest contiguous segment. Additional projects are under design to extend the path further through Woonsocket, connecting existing segments, as well as through the cities of Providence, Pawtucket, and Central Falls.
Construction was delayed due to a lack of state funds, a shortfall attributed to the over-budget "Big Dig" highway tunnel project in Boston.[7] In 2005, as part of the Massachusetts Turnpike-Route 146 interchange project, the first 2.5-mile (4.0km) segment, from Worcester to Millbury, was opened to the public.
In 2010, an agreement was reached between MassDOT and DCR for DCR to take over the management of the design and environmental permitting of Sections 1 through 5 of the Greenway, including preparation of the Environmental Impact Report (EIR). Section 6 was previously constructed by MassDOT, and Section 7 will be designed by the City of Worcester, and constructed by MassDOT.
In 2013, five bridges in Blackstone that run concurrently with the Southern New England Trunkline Trail (SNETT) were repaired and repainted. These are the two Factory Pond Bridges, the northern Canal Street Bridge, a Blackstone River Bridge, and the St. Paul Street Bridge. By September 2014, these bridges received new ipe wood decks and safety railings. In 2014, new bridges were also constructed over Kane Court and Main Street, and a tunnel was built under Church Street, all in the town of Blackstone. The entire 3.7-mile path was finally completed in December 2016.[8] Restoration work on the Blackstone Viaduct, located adjacent to the southern terminus of this path, began in 2019. When completed, this project will add approximately 0.5 miles of bike path extending to the Rhode Island border, where it will connect with an existing segment of path in Woonsocket.[9]
All of the trail between the missing Blackstone River and Rte. 122 bridge in Blackstone and Rte. 146A in Uxbridge is part of both the SNETT and the Blackstone River Greenway.