Dungeness_Nuclear_Power_Station

Dungeness nuclear power stations

Dungeness nuclear power stations

Decommissioned nuclear power plant in England


The Dungeness nuclear power stations are a pair of non-operational nuclear power stations located on the Dungeness headland in the south of Kent, England.

Dungeness A & B nuclear power stations

Dungeness A is a legacy Magnox power station consisting of two 250 MWe reactors which were connected to the National Grid in 1965 and reached its end of life in 2006.

Dungeness B is an advanced gas-cooled reactor (AGR) power station consisting of two 520 MWe reactors, which began operation in 1983 and 1985. They were the first in a series of AGR reactors to be constructed across the UK. In March 2009, unexpected problems discovered during a maintenance shutdown on unit B21 resulted in the reactor remaining offline for nearly 18 months. In 2015, the plant received upgrades and was given a second ten-year life extension to 2028. In September 2018, as both units were shut down for a scheduled maintenance outage, EDF encountered "significant and ongoing technical challenges" which ultimately led to the announcement of its closure on 7 June 2021.

Dungeness A

Quick Facts Country, Location ...

Dungeness A is a legacy Magnox power station that was connected to the National Grid in 1965 and has reached the end of its life. It possessed two nuclear reactors producing 219 MW of electricity each, with a total capacity of 438 MW.[1] The construction was undertaken by a consortium known as the Nuclear Power Group ('TNPG').[2] The reactors were supplied by TNPG and the turbines by C. A. Parsons & Co.[1] There were originally four × 142.5 MW turbo-alternators, these were later down-rated to 106 MW machines.[3] Steam pressure and temperature at the turbine stop valves was 535 psi (36.9 bar) and 391 °C (736 °F).[3]

Electricity output

Electricity output from Dungeness A power station over the period 1966-84 was as follows.[3]

Dungeness A annual electricity output GWh.

Nuclear fuel for Dungeness power stations can be delivered and removed via a crane loading facility at the end of the 9-mile (14 km) Appledore-Lydd-Dungeness branch railway. This is connected to the Ashford to Hastings line via an east-facing junction located to the west of Appledore station. The close proximity of the Appledore-Lydd-Dungeness branch to the nuclear power stations allow for a more direct route to and from major fuel fabrication sites all whilst minimising the use of road convoys thus lowering traffic impact on nearby communities.[4]

Closure and decommissioning

On 31 December 2006, Dungeness A ceased power generation after over 40 years of operation. Defuelling was completed in June 2012, with all fuel having been sent to Sellafield for reprocessing.[5] After the site was declared fuel-free, demolition works accelerated beginning with the demolition of the turbine hall in June 2015.[6] Similar to other legacy Magnox stations, the site will undergo decommissioning where radiologically contaminated equipment is removed and redundant structures demolished. Once complete, the reactor buildings will be re-cladded to ensure they are able to remain an effective barrier to the elements and the facility will enter a 'care and maintenance' stage.

The care and maintenance stage is part of the Nuclear Decommissioning Authority (NDA) decommissioning strategy and spans an 80+ year period. This waiting period allows for radiation levels within the reactor core to decline and helps to facilitate a smoother demolition process. Dungeness A is due to enter the care and maintenance phase in 2027. Demolition of reactor buildings and final site clearance is planned for 2088 to 2098.[7] The ongoing decommissioning process is being managed by Magnox Ltd, a subsidiary of the NDA.

Dungeness B

Quick Facts Country, Location ...

Dungeness B is an advanced gas-cooled reactor (AGR) power station consisting of two 1,496 MWt reactors, which began operation in 1983 and 1985 respectively. Dungeness B was the first commercial scale AGR power station to be constructed. Its design was based on the much smaller Windscale AGR prototype, the WAGR. The £89 million contract was awarded in August 1965 to Atomic Power Construction ('APC'),[10] a consortium backed by Crompton Parkinson, Fairey Engineering, International Combustion and Richardsons Westgarth.[2] The completion date was set as 1970.

During construction, many problems were encountered in scaling up the WAGR design. Problems with the construction of the pressure vessel liner had distorted it, so that the boilers, which were to fit in an annular space between the reactor and the pressure vessel, could not be installed, and the liner had to be partially dismantled and rebuilt. This work cost about £200,000, but there was a huge cost of financing an extra 18 unproductive months for a power station costing around £100 million, of which 60% was already complete.[11] Serious problems were also discovered with the design of the boilers, which had to withstand the pounding of hot carbon dioxide (CO2), pressurised to 600 pounds per square inch (4,100 kPa) and pumped around the reactor coolant circuit by massive gas circulators. As a consequence, the casings, hangers and tube supports all had to be redesigned. The cost of the modifications, and financing during the delays, caused severe financial pressures for the consortium and its backers, and in 1969 APC collapsed into administration.

The CEGB took over project management, imposed light penalties in order not to cripple Fairey and International Combustion, and appointed British Nuclear Design and Construction (BNDC) as main contractor. In 1971, problems with corrosion of mild steel components in the first generation Magnox reactors gave the designers cause for concern. The Dungeness B restraint couplings - mechanical linkages that held the graphite core in place whilst allowing it to expand and contract in response to temperature changes - were made of mild steel and could be subject to the same corrosion. It was decided to replace them with components made from a new material.[12] In 1972, problems were found with the galvanised wire that was used to attach thermocouples to stainless steel boiler tubes. During heat treatment of the tubes at temperatures up to 1,050 °C (1,920 °F), the galvanising zinc diffused into the tubes and made them brittle. The cost had by then risen to £170 million.[13] By 1975, the CEGB was reporting that the power station would not be completed until 1977 and that its cost had risen to £280 million.[14] By 1979, the cost had risen further to £410 million.[15]

Reactor 1 first generated power on 3 April 1983, 13 years behind schedule and at a cost of £685 million, four times the initial estimate in inflation-adjusted terms.[16] The original construction consortium had collapsed.[17]

As with the "A" station, the turbines were built by C.A. Parsons & Company[1] and the station has two 660 MWe turbo-alternator sets, producing a maximum output of 1,320 MWe,[8] though net output is 1,090 MWe after the effects of house load, and downrating the reactor output due to corrosion and vibration concerns.[18]

In 2005, the station's closure date was extended from 2008 by ten years, which would allow it to continue operating until 2018, 35 years after first power generation.[19]

In March 2009, serious problems were found when Unit 21 was shut down for maintenance, and the reactor remained out of action for almost 18 months.[20][21] On 24 November 2009, a small fire in the boiler annexe of Unit 22 caused the second reactor to be shut down as well. Subsequently, Unit 22 has been intermittently shut down for up to several months at a time. Unit 21 was restarted in August 2010.[22][23][24] Unplanned shutdowns continued into 2011,[25][26] with 21 down for repairs from November 2011 to March 2012.[27]

In 2015, the plant was given another ten-year life extension, allowing an upgrade to control room computer systems and improved flood defences, taking the accounting closure date to 2028.[28]

Electricity output

In 2015, Dungeness B produced 4.4 TWh of energy. The operators claimed that this amounted to a saving of 3.4 million tonnes of CO2.[29]

Decommissioning

In September 2018, the Office for Nuclear Regulation (ONR) directed that EDF Energy carry out a reassessment of corrosion of safety-related concealed systems. Inspections showed that seismic restraints, pipework and storage vessels were found to be "corroded to an unacceptable condition", and that would have been the state when the reactor was operating. Remedial measures included the upgrading of more than 300 metres (980 ft) of pipeline and of carbon dioxide storage vessels. The ONR classified this as a level 2 incident on the International Nuclear Event Scale. Dungeness B was initially expected to return to service in February 2019,[30][31] later put back to 30 September 2019 to complete inspections.[32] In August 2020, the shut down of units B21 and B22 was extended to December 2020 after being taken offline in September 2018.[33]

On 7 June 2021, EDF announced that Dungeness B would not be restarted and would move into the defuelling phase immediately, once regulatory permissions are granted, citing "station-specific risks within some key components, including parts within the fuel assemblies" identified since September 2018.[34][35][36]

EDF has estimated the cost of defuelling Dungeness B at £0.5£1.0 billion,[37] with the process expected to take up to ten years.[38] A UK Parliament committee report noted that the cost of decommissioning is shouldered in part by UK taxpayers.[39]

Consideration of Dungeness C

On 15 April 2009, Dungeness was included in a list of 11 potential sites for new nuclear power stations, at the request of EDF Energy, which owns and operates Dungeness B.[40] The government did not include Dungeness C in its draft National Policy Statement published on 9 November 2009, citing environmental reasons and concerns about coastal erosion and associated flood risk.[41] The site was ruled out by Secretary of State for Energy and Climate Change Chris Huhne in October 2010, with the former government's list of eleven potential sites reduced to eight.[42] Despite these environmental concerns, local Conservative MP Damian Collins, supported by some residents, lobbied Parliament to reconsider that position.[43][44]

HVDC station

From 1961 to 1984, Dungeness power station also housed the mercury arc valves of the static inverter plant converting AC into DC for transmission on HVDC Cross-Channel, the high-voltage direct current power cable carrying electric power across the English Channel to France. In 1983, a more powerful new inverter at Sellindge replaced this facility.

Ownership

Both stations were originally built, owned, and operated by the CEGB. Following privatisation of the electricity supply industry and the later part-privatisation of the nuclear power generating industry they are now owned by two different bodies: the original Magnox station Dungeness A by the non-departmental government body the NDA and newer AGR Dungeness B by EDF Energy.

Location

The stations are built on a large area of open shingle, measuring 12 by 6 kilometres (7.5 by 3.7 mi), which has been deposited by the sea and built up over thousands of years. The entire area is moving slowly north and east as the sea moves the shingle from one side of the headland to the other. It is surrounded by a nature reserve Site of Special Scientific Interest (SSSI). A fleet of lorries is used to continuously maintain shingle sea defences for the plant as coastal erosion would otherwise move shingle away at an estimated rate of 6 metres (20 ft) per year. Around 30,000 cubic metres (39,000 cu yd) of shingle are moved each year. It seems that deposition on the north shore of the headland does not keep pace with erosion, although the power stations are about 1 kilometre (0.62 mi) to the west of that shore. In all, 90,000 cubic metres (120,000 cu yd) are moved each year along parts of the coast between Pett Level and Hythe. This is necessary for the safety of the entire area including the power stations. During operation, around 100 million litres (22×10^6 imp gal) of cooling water was extracted and returned to the sea each hour, after being heated by 12 °C (22 °F).

The headland and the coastline between Pett Level and Hythe are volatile. In recorded history Walland Marsh to the west of the power stations has been flooded.[45] In the space of sixty years severe inundation occurred, temporarily bringing the sea inland to Appledore and the original mouth of the River Rother from north of the headland at Romney to the south at Rye Harbour. The site is a few metres above Mean Sea Level and would be isolated in the event of flooding of the magnitude that submerged large areas of East Anglia and the Netherlands in 1953. It has been conjectured[who?] that the Great Storm of 1987 did not bring the sea to the stations because there was a low tide at the time. Climate change could cause more frequent and powerful storms, and associated waves and surges are possible though not probable, and might increase the instability of the headland.[45]

In the media

The station was used in the filming of the Doctor Who serial The Claws of Axos in January 1971.[46]

The site provides a key plot point in the 2016 book, Alan Partridge: Nomad.[47]

The station is within sight of artist Derek Jarman's garden at Prospect Cottage.[48] The film The Garden was filmed at the house,[49] and it was the main subject of an episode of BBC's Countryfile in February 2020.[50]

See also


References

  1. "Industcards.com". www.industcards.com. Archived from the original on 19 July 2009. Retrieved 23 August 2014.
  2. "The UK Magnox and AGR Power Station Projects" (PDF). Archived from the original (PDF) on 27 April 2020. Retrieved 21 September 2010.
  3. CEGB Statistical Yearbook (various dates). CEGB, London.
  4. Jacobs, Gerald (2008). Railway Track Diagrams Book 5: Southern and TfL. Bradford on Avon: Trackmaps. pp. 18D. ISBN 9780954986643.
  5. "Decommissioning progress at Dungeness A". World Nuclear News. World Nuclear Association. 21 January 2015. Retrieved 1 September 2015.
  6. "Dungeness A turbine hall bites the dust". NDA. Nuclear Decommissioning Authority. 23 June 2015. Retrieved 1 September 2015.[permanent dead link]
  7. "The 2010 UK Radioactive Waste Inventory: Main Report" (PDF). Nuclear Decommissioning Agency/Department of Energy & Climate Change. February 2011. Archived from the original (PDF) on 25 March 2012. Retrieved 22 May 2012.
  8. Nonbel, Erik. "Description of the Advanced Gas Cooled Type of Reactor (AGR)" (PDF). IAEA. nks (Nordic Nuclear Safety Research). Archived from the original (PDF) on 9 June 2022. Retrieved 12 February 2020.
  9. "Dungeness B EDF Energy". Retrieved 28 April 2014.
  10. "Events - World Nuclear Association". www.world-nuclear.org. Archived from the original on 2 October 2012. Retrieved 11 April 2009.
  11. The Times, Tuesday, 10 December 1968; pg. 24; Issue 57430; col A
  12. The Times, Thursday, 11 March 1971; pg. 19; Issue 58119; col E
  13. The Times, Saturday, 4 November 1972; pg. 19; Issue 58623; col C
  14. The Times, Thursday, 6 November 1975; pg. 20; Issue 59546; col A
  15. The Times, Wednesday, 23 January 1980; pg. 3; Issue 60531; col E
  16. "The Atom in Red, White and Blue". Nuclear Engineering International. 12 October 2022. Retrieved 8 November 2022.
  17. "EDF". EDF. Archived from the original on 1 May 2006.
  18. 10-year life extension at Dungeness B nuclear power station, British Energy, 15 September 2005, archived from the original on 22 March 2006, retrieved 19 June 2008
  19. "Fire shuts nuclear power station". BBC. 24 November 2009. Retrieved 24 November 2009.
  20. "UPDATE 1-UK Hunterston B7 nuclear unit restarts Fri". Reuters. 5 March 2011. Archived from the original on 30 August 2012.
  21. "UK Dungeness 22 unit back on grid since Jul 24-EDF". Reuters. 1 August 2011. Archived from the original on 23 September 2012.
  22. "ABLE-UK nuclear power plant outages". Reuters. 25 November 2011.
  23. "UK nuclear plant gets ten-year extension". World Nuclear News. 20 January 2015. Retrieved 21 January 2015.
  24. "EDF Energy announces 10 more years for Dungeness B". EDF France. 3 June 2015. Retrieved 21 May 2020.
  25. "Dungeness B corrosion rated at INES level 2". Nuclear Engineering International. 24 January 2019. Retrieved 30 January 2019.
  26. "External corrosion affecting multiple systems on a power reactor". Office for Nuclear Regulation. IAEA. 31 December 2018. Retrieved 30 January 2019.
  27. "Outage extensions for UK's Dungeness and Hunterston". Nuclear Engineering International. 12 March 2019. Retrieved 18 March 2019.
  28. "More delays for restart of UK's Hunterston and Dungeness NPPs". Nuclear Engineering International. 12 August 2020. Retrieved 15 August 2020.
  29. "EDF decides to move Dungeness B into defuelling phase". EDF Energy. 7 June 2021. Retrieved 7 June 2021.
  30. Varley, James (2 May 2022). "AGR reactors: Examining decommissioning costs of UK fleet". Retrieved 11 June 2022.
  31. "Dungeness B: Kent's last nuclear power station closes early". BBC News. 8 June 2021. Retrieved 7 March 2024.
  32. Laville, Sandra (20 May 2022). "UK nuclear power stations' decommissioning cost soars to £23.5bn". The Guardian. Retrieved 11 June 2022.
  33. "Dungeness among 11 sites for new nuclear power station". Kent and Sussex Courier. This is Kent. 15 April 2009. Archived from the original on 23 September 2015. Retrieved 1 September 2015.
  34. "Nuclear power: Eight sites identified for future plants". BBC News. 18 October 2010. Retrieved 18 October 2010.
  35. Eddison, J (2000). Romney Marsh Survival on a Frontier. Tempus. p. 139. ISBN 0-7524-1486-0.
  36. Mark Braxton (28 October 2009). "Doctor Who: The Claws of Axos". Radio Times. Retrieved 13 December 2012.
  37. Billinghurst, Jane (2011). Armchair Book of Gardens: A Miscellany. Rowman & Littlefield. ISBN 978-0-7627-6782-3.
  38. "Countryfile - Dungeness" via www.bbc.co.uk.

Other sources

  1. Eddison, J (2000). Romney Marsh Survival on a Frontier. Tempus. ISBN 0-7524-1486-0. Page 139 also reports the 1990 flooding mentioned above. Page 139 also reports the 1990 flooding mentioned above.
  2. "Romney Marsh". Retrieved 5 February 2006.
  3. "Kent Against a Radioactive Environment". Archived from the original on 24 April 2006. Retrieved 20 March 2006.
  4. "British Energy". Archived from the original on 28 September 2007. Retrieved 16 April 2006.
  5. "industcards". Retrieved 16 April 2006.[permanent dead link]
  6. "Going Critical" (PDF). Retrieved 16 April 2006.

Share this article:

This article uses material from the Wikipedia article Dungeness_Nuclear_Power_Station, and is written by contributors. Text is available under a CC BY-SA 4.0 International License; additional terms may apply. Images, videos and audio are available under their respective licenses.