Ferguson Marine (Port Glasgow) Limited is a shipbuilding company whose yard, located in Port Glasgow on the Firth of Clyde in Scotland, was established in 1903. It is the last remaining shipbuilder on the lower Clyde and is currently the only builder of merchant ships on the river. For some years the company's mainstay has been Roll-on/roll-off ferries, primarily for Caledonian MacBrayne (CalMac), including a series of innovative hybrid diesel-electric/battery-powered vessels. Beset with difficulties since 2018 over their latest two CalMac ferries, Fergusons' largest ever vessel, the shipyard was nationalised in December 2019. It is now classified as an executive non-departmental public body of the Scottish Government.[1]

Quick Facts Company type, Industry ...
Ferguson Marine Engineering from the west, behind Newark Castle, prior to the November 2017 launch of MV Glen Sannox.

History

The Ferguson shipyard was founded as a partnership by four Ferguson Brothers (Peter, Daniel, Louis and Robert) who left the Fleming & Ferguson shipyard in Paisley to lease the Newark yard in Port Glasgow in March 1903.[2][3] Ferguson Brothers acquired the freehold in the yard in 1907 and was incorporated as Ferguson Brothers (Port Glasgow) Ltd in 1912.[3] The company was purchased by John Slater Ltd (Amalgamated Industries) in 1918[3] but returned to control of the Ferguson family in the late 1920s. Lithgows Ltd purchased an interest in the business after Bobby Ferguson's death in 1954[2] and took control of the Company in 1961.[3] Ferguson Brothers remained a separate entity within the Scott Lithgow group from 1969 to 1977.[2]

Entrance to Ferguson Shipbuilders, with the original office building and fabrication shed built to the line of the railway branch which once served the harbour.

The company was nationalised and subsumed into British Shipbuilders in 1977,[3] then merged with the Ailsa Shipbuilding Company to form Ferguson-Ailsa Ltd in 1980.[2]

Ferguson Shipbuilders Ltd

Ferguson and Ailsa were separated in 1986 when the latter yard was sold and Ferguson was merged with Appledore Shipbuilders in Devon to form Appledore Ferguson Shipbuilders Ltd.[3] By the late 1980s only the Appledore Ferguson yards were still held in state ownership.[4] Ferguson was demerged from Appledore and acquired by Greenock-based engineering firm Clark Kincaid in 1989 then started trading as Ferguson Shipbuilders.[2][3]

Clark Kincaid itself was acquired by Kvaerner and became Kvaerner Kincaid in 1990,[5] and the Ferguson yard sold to Ferguson Marine plc in 1991.[3] The entire shareholding in Ferguson Marine was acquired by the Holland House Electrical Group in 1995.[6] The sign above the main gate continued the name Ferguson Shipbuilders Limited.[7] Between 2013 and 2016 the yard built three hybrid diesel-electric/battery powered ferries, beginning with Hallaig - the world's first.[8]

Ferguson Marine Engineering Ltd.

2017 view of new office building and shipyard entrance, extended nearer the A8 road.

In August 2014, the shipyard placed the company into administration and the following month Clyde Blowers Capital, an industrial company owned by Jim McColl, purchased the yard for £600,000 and renamed it Ferguson Marine Engineering Ltd (FMEL).[7]

In August 2015, government-owned Caledonian Maritime Assets Limited (CMAL) announced that an order for two ferries for Caledonian MacBrayne service, capable of operating on either marine diesel oil or liquefied natural gas, had been won by Fergusons.[9] Originally intended for delivery during 2018, construction difficulties (the reasons for which are in dispute) led to a two-year delay for the first ship, Glen Sannox, which was launched in November 2017.[10][11]

FMEL was part of two consortia's bids for the programme for five type 31 frigates for the Royal Navy, worth some £1.25 billion. The consortia are those led by Babcock International and Atlas Elektronik UK.[12] After their bid was selected, a contract was formally awarded to Babcock Group on 15 November 2019, for an average production cost of £250 million per ship and an overall programme cost set to be £2 billion.[13]

On 30 October 2018, FMEL secured a contract to construct a large air cushioned barge for Mangistau ACV Solutions Ltd, part of the CMI Offshore Ltd Group, with estimated completion scheduled in 2019.[14] In December 2018 FMEL announced that two orders worth £5.4 million had been secured from Inverlussa Marine Services for fish farm support ships, to be completed in May 2019, and that three more for fishing vessels, totaling £11 million, were in the pipeline.[15] By July 2019 the ferry dispute had led to delays in closing the trawler contracts.[16]

Ferguson Marine from the west, Newark Quay seen across Coronation Park in 2017.

Attempts by Clyde Blowers Capital to negotiate with the Scottish Government over increased costs and delays to ferries failed, and on 9 August 2019 the directors of FMEL gave notice that the company would be put into administration.[11] This led to a bitter dispute between the Scottish Government and the former owners of the shipyard.[17] A week later the Scottish Government announced that they would take over management of the yard to allow work to continue on current orders, and that if no private buyer could be found in four weeks, the yard would be nationalised by purchase.[18] At the start of December, after three private bids to purchase the yard were rejected as being insufficiently favourable to creditors, the government formally took ownership of the shipyard, and in the process wrote off about £50 million of previous loans.[19]

Ferguson Marine (Port Glasgow) Ltd.

Shipyard entrance in 2021, mobile crane lifts section onto Hull 802

The newly nationalised shipyard was renamed Ferguson Marine (Port Glasgow) Ltd. on 2 December 2019.[19] The costs and viability of completing contracts was investigated, and Tim Hair was appointed as turnaround director. On 22 January 2020 he told a Scottish Parliament inquiry that the large ferries MV Glen Sannox and Hull 802 were "significantly less than half built", with 95% of their design still to be agreed with the client body Caledonian Maritime Assets. Additional naval architects and marine engineers had been engaged to complete this design work.[20]

In March 2020 Ferguson Marine announced that they had taken a four year lease on a large warehouse sited at Greenock waterfront, and would use it to consolidate stock and materials which had been stored in several warehouses near Glasgow Airport.[21] The large air cushioned barge for CMI Offshore Ltd (ordered from FMEL in 2018) was launched on 24 June 2020, to be taken to the Caspian Sea to be completed and outfitted for oil exploration work in that area.[22]

The company's board of directors with six non–executive members, including Alistair Mackenzie as chairman, was appointed in June 2020 by the Scottish Government Cabinet Secretary Fiona Hyslop.[23]

Hull 802 in December 2021

In February 2021, the firm announced it would take on 120 additional workers with the intention of operating seven days per week.[24] The bulbous bow of Hull 802 was fitted in September 2021, and reported as a landmark in significant progress to both ships, deliveries of which by January 2022 were running up to five years late.[25][26]

Fergusons had bid for two new ferries to be ordered by CMAL, but was not included on the shortlist to submit detailed tenders.[27] On 16 December David Tydeman was appointed chief executive, to take over from Tim Hair in February 2022.[28]

On 16 March 2023, Tydeman wrote to Scottish Ministers requesting a reset of the timetable for delivery of the two ferries to no later than end 2023 for Glen Sannox (Hull 801) and no later than end 2024 for Hull 802. The shipyard is aiming to delivering earlier – Glen Sannox in autumn 2023 and Hull 802 before late summer 2024.[29]

In May 2023, Ferguson announced that it had secured an initial contract with BAE Systems to fabricate three steel units for HMS Belfast, the third City Class Type 26 frigate currently being constructed by BAE Systems.[30]

List of vessels built under Ferguson Marine Engineering Ltd (since 2014)

More information Yard No., Name ...

List of vessels built under Ferguson Shipbuilders Ltd (1991 - 2014)

More information Yard No., Name ...

List of vessels built under Appledore Ferguson Shipbuilders Ltd (1986 - 1989)

More information Yard No., Name ...

List of vessels built under Ferguson-Ailsa Ltd (1983 - 1986)

More information Yard No., Name ...

List of vessels built under Ferguson Brothers (Port Glasgow) Ltd (1912 - 1983)

More information Yard No., Name ...

See also

Ferry fiasco - for the Scottish political controversy around the construction of the Glen Sannox and Glen Rosa.


References

  1. "National public bodies directory - Executive non-departmental public bodies". Scottish Government. 26 July 2022. Retrieved 25 August 2022.
  2. Goodwin, Karin (5 March 2007). "History of a shipbuilding family". BBC News.
  3. Middlemiss, Norman L (July 1994). British shipbuilding yards, vol 2: Clydeside (1st ed.). Newcastle-upon-Tyne: Shield Publications Ltd. pp. 239–243. ISBN 1871128110.
  4. "Why Scotland must redesign its vision of shipbuilding to become industry leader again". The Herald on Sunday. 7 September 2014. Retrieved 13 July 2019.
  5. "Port Glasgow, Ferguson Ailsa Shipyard". Canmore. Retrieved 13 July 2019.
  6. "Name Announced For New Ferry". Inverclyde Now. 4 October 2012. Archived from the original on 6 October 2012. Retrieved 13 January 2013.
  7. "IN Pictures -- Launch Of Ferry Glen Sannox At Port Glasgow". Inverclyde Now. 21 November 2017. Archived from the original on 21 November 2017. Retrieved 21 November 2017.
  8. "Clyde shipyard Ferguson set to go into administration". BBC News. 9 August 2019. Retrieved 16 August 2019.
  9. "How many ships are the Clyde shipyards expecting to build?". UK Defence Journal. 25 February 2019. Retrieved 13 July 2019.
  10. Vavasseur, Xavier (15 November 2019). "UK MoD Formally Awards Type 31 Frigate Contract To Babcock". Naval News. Retrieved 16 November 2019.
  11. "Ferguson Marine Engineering Secures Contract to Build Air Cushion Barge - Home - EN". Clyde Blowers Capital. 30 October 2018. Retrieved 27 June 2020.
  12. "Ferguson Marine wins contract to build two new vessels". Greenock Telegraph. 25 December 2018. Retrieved 13 July 2017.
  13. "Ferry dispute threatens last civilian shipyard on the Clyde". Financial Times. 7 July 2019. Retrieved 13 July 2017.
  14. "Ferguson shipyard nationalised by Scottish government". BBC. 16 August 2019. Retrieved 16 August 2019.
  15. "Ferguson Marine shipyard taken into public ownership". BBC News Online. 2 December 2019. Retrieved 11 April 2020.
  16. "Ferries are a 'long way off completion', MSPs warned". BBC News. 22 January 2020. Retrieved 27 June 2020.
  17. "Shipyard Signs Major Greenock Waterfront Warehouse Deal". Inverclyde Now. 9 March 2020. Retrieved 16 March 2020.
  18. "Air Cushion Barge Launch At Port Glasgow". Inverclyde Now. 24 June 2020. Retrieved 27 June 2020.
  19. "Board Of Directors Appointed For Ferguson Marine Yard". Inverclyde Now. 26 June 2020. Retrieved 27 June 2020.
  20. "Nationalised Ferguson shipyard to recruit 120 extra workers". BBC News. 25 February 2021. Retrieved 26 February 2021.
  21. "Further 'Significant' Progress On Ferguson Ferries". Inverclyde Now. 1 September 2021. Retrieved 28 December 2021.
  22. Williams, Martin (30 January 2022). "How Ferguson Marine ferry fiasco vessel Glen Sannox was involved in a Storm Malik river drama". The Herald. Glasgow. Archived from the original on 7 February 2022. Retrieved 7 February 2022.
  23. Watson, Calum (14 September 2021). "Nationalised shipyard misses out on ferries order". BBC News. Retrieved 28 December 2021.
  24. "New Boss To Take The Helm At Ferguson Marine". Inverclyde Now. 16 December 2021. Retrieved 28 December 2021.
  25. "Ferguson Marine quarterly report". www.parliament.scot. Retrieved 16 May 2023.
  26. "Ferguson Marine update: Ministerial statement". www.gov.scot. Retrieved 16 May 2023.
  27. "Vessel list". www.clydeships.co.uk. Retrieved 8 November 2023.
  28. Inverlussa, Marine Services. "MV Helen Rice Specification" (PDF). www.inverlussa.com. Retrieved 8 November 2023.
  29. Inverlussa, Marine Services. "MV Kallista Rice Specification" (PDF). www.inverlussa.com. Retrieved 8 November 2023.
  30. "Vessel list". www.clydeships.co.uk. Retrieved 7 November 2023.
  31. "Vessel list". www.clydeships.co.uk. Retrieved 7 November 2023.
  32. "Vessel list". www.clydeships.co.uk. Retrieved 11 November 2023.
  33. "Vessel list". www.clydeships.co.uk. Retrieved 11 November 2023.
  34. "Vessel list". www.clydeships.co.uk. Retrieved 11 November 2023.

Share this article: