Hinkley_Point_B_nuclear_power_station

Hinkley Point B nuclear power station

Hinkley Point B nuclear power station

Offline nuclear power plant located in Somerset, England, UK


Hinkley Point B nuclear power station was a nuclear power station near Bridgwater, Somerset, on the Bristol Channel coast of south west England. It was the first commercial Advanced Gas Cooled reactor to generate power to the National Grid in 1976 and shares its design with sister station Hunterston B nuclear power station. It ceased operations permanently on 1 August 2022.[4]

Quick Facts Country, Location ...

History

The construction of Hinkley Point B, which was undertaken by a consortium known as The Nuclear Power Group (TNPG),[5] started in 1967. The reactors vessels were supplied by Whessoe, reactor machinery was supplied by Strachan & Henshaw and the turbines by GEC.[6]

In March 1971, it was announced that there would be a six-month delay in completion due to problems with the insulation of the concrete pressure vessel. In place of the stainless steel mesh and foil insulation that had been used on previous Magnox stations, a fibrous type of insulation supplied by Delaney Gallay, part of the Lindustries Group, had been used for the first time. During pre-operational trials, before the nuclear fuel was loaded, high levels of acoustic vibration in the gas circuit were found to be damaging the insulation tiles, and the retention plates which held the insulation in place had to be redesigned and modified within the reactor.[7]

During further pre-operational testing, severe vibration of the fuel channel gags was detected. The fuel channel gags are valves which are gradually closed to restrict the flow of gas through a fuel channel in order to maintain the channel gas outlet temperature as the nuclear fuel is used up. Modifications to produce a fluidically generated bias force to stop the gags vibrating took time to design, test and implement, delaying the planned start up date.[8] The station began generating electricity on 5 February 1976.

It was taken over by Nuclear Electric as part of the privatisation of the UK Electricity Supply Industry in 1990, though remaining in public ownership at that time. In 1996, the AGR and PWR assets of Nuclear Electric and Scottish Nuclear were privatised as part of British Energy.

In 2006, the station's reactors were shut down in order to inspect the boilers for weld defects that had been found in power stations using similar boiler designs. Due to its age, on 16 August 2006 the company warned that until a decision was made over whether to extend its usable life it would operate at a maximum of 70 per cent load. Both reactors were subsequently restarted generating 420 MW each, roughly 70% of full capacity. The number 4 reactor was cleared for restart by the Nuclear Installations Inspectorate on 11 May 2007. [9] The power station's closure date was 2023 for a time, before it closed a year earlier.[10]

In July 2013, EDF Energy announced that the load on both of the station reactors had been increased to 80 per cent, resulting in an output of around 485-500 MWe per reactor up from 70% load, where it had been generating around 420 MWe per reactor since 2006.[11]

Hinkley Point B was the last of four nuclear power stations in the area to cease operations. Three Magnox power stations being decommissioned are the adjacent Hinkley Point A, and Oldbury nuclear power station and Berkeley nuclear power station on the banks of the River Severn.

In October 2016, it was announced that super-articulated control rods would be installed in the reactor because of concerns about the stability of the reactors' graphite cores. The Office for Nuclear Regulation (ONR) had raised concerns over the number of fractures in keyways that lock together the graphite bricks in the core. An unusual event, such as an earthquake, might destabilise the graphite so that ordinary control rods that shut the reactor down could not be inserted. Super-articulated control rods should be insertable even into a destabilised core.[12]

Specification

The station is of the advanced gas-cooled reactor (AGR) type with two 1,600 MWt reactors, each with their own 660 MWe steam turbine generator set giving a combined maximum design generating capacity of 1,250 MW. As of 2013, it provided over 1% of the UK's total power output.[13]

Hinkley Point B is also equipped with four 17.5 MW Rolls-Royce Olympus industrial gas turbines. Installed in 1970/71, and originally used for 'peak lopping', these are now used exclusively as emergency standby generators for the station.[14]

Comparison with Hinkley Point A

A comparison with Hinkley Point A is shown below.[15] See also comparison of Hinkley Point A, B and C

More information Parameter ...

Capacity and output

The generating capacity, electricity output, load factor and thermal efficiency was as shown in the table.[16]

More information Year, Net capability, MW ...

Closure

On 19 November 2020, EDF announced that Hinkley point B would stop generating electricity and move into the defuelling phase no later than 15 July 2022.

"Running a nuclear power plant this efficiently for over 40 years leads to changes in the reactors. Our inspections of Hinkley’s reactor cores this year show that the graphite blocks are in exactly the sort of condition we predicted they would be at this stage in the station’s lifetime. As a responsible operator we feel it is now the right thing to do to give clarity to our staff, partners and community about the future life of the station, which is why we have made this proactive decision. I would like to pay tribute to all those associated with Hinkley Point B for their outstanding professionalism and wish them well with the next chapter."

Matt Sykes, Managing Director of EDF Generation

The plant has operated for 45 years and produced over 300 TWh over its lifetime.[17][18][19] Reactor B-8 was shut down in July 2022, followed by reactor B-7 in August. EDF said that the defueling process could take a few years, and the removed fuel will be given to the Nuclear Decommissioning Authority for decommissioning.[20][21]

Hinkley Point C

A new 3,260 MW Hinkley Point C nuclear power station, consisting of two EPR reactors, was given planning consent on 19 March 2013.[22] A guaranteed "strike price" of £92.50 per megawatt-hour (to be indexed for inflation over 45 years) was announced on 21 October 2013. The new power station would see Hinkley's contribution to the country's power supply rise to 7%.[13] At the time of the planning consent, the price for electric energy on the wholesale market was around £45 per megawatt-hour while the new power plant was expected to need earnings of £90 per megawatt-hour in order to break even.[23]

On 8 October 2014, the EU gave its consent to the 'Contract for Difference (CFD)' that guarantees the "strike price".[24]

See also


References

  1. "HINKLEY POINT B-1". Public Reactor Information System. IAEA. 29 August 2022. Retrieved 30 August 2022.
  2. "HINKLEY POINT B-2". Public Reactor Information System. IAEA. 29 August 2022. Retrieved 30 August 2022.
  3. World Nuclear News (1 August 2022). "Hinkley Point B enters retirement". World Nuclear News. Retrieved 30 August 2022.
  4. "Hinkley B: UK's most productive nuclear power plant closes". BBC News. 1 August 2022. Retrieved 10 August 2022.
  5. "Nuclear Development in the United Kingdom". World Nuclear Association. Retrieved 28 December 2013.
  6. "Nuclear Power Plants in the UK". Industcards.com. Archived from the original on 19 July 2009. Retrieved 20 October 2013.
  7. The Times, Tuesday, 30 March 1971
  8. The Times, Thursday, 13 February 1975
  9. "Nuclear plant gets nod to restart". BBC. 11 May 2007. Retrieved 31 May 2007.
  10. "Hinkley Point B and Hunterston B return to 80% load". NucEngInt. 1 July 2013. Retrieved 12 May 2015.
  11. "Nuclear reactor cracks 'challenge safety case'". BBC News. 31 October 2016. Retrieved 31 October 2016.
  12. "UK nuclear power plant set for go-ahead". bbc.co.uk. 13 October 2013. Retrieved 20 October 2013.
  13. Hinkley Point B Nuclear Power Station. London: Central Electricity Generating Board. April 1971. p. 4.
  14. CEGB Statistical Yearbook 1979-84, CEGB London
  15. "UK's Hinkley Point B to be retired by July 2022". World Nuclear News. 19 November 2020. Retrieved 19 November 2020.
  16. "Why close Hinkley Point B early?". Nuclear Engineering International. 3 March 2021. Retrieved 12 March 2021.
  17. "BMRS (Hinkley B T/A 8 Scheduled Closure Date)". BMRS. ELEXON. 22 June 2022. Retrieved 30 June 2022.
  18. Harvey, Dave Harvey (19 March 2013). "What price nuclear power? The final hurdle for Hinkley". BBC. Retrieved 19 March 2013.

Share this article:

This article uses material from the Wikipedia article Hinkley_Point_B_nuclear_power_station, and is written by contributors. Text is available under a CC BY-SA 4.0 International License; additional terms may apply. Images, videos and audio are available under their respective licenses.