The LGV Rhin-Rhône (French: Ligne à Grande Vitesse; English: high-speed line) is a French high-speed rail line, the first in France to be presented as an inter-regional route rather than a link from the provinces to Paris,[1] though it actually is used by some trains to/from Paris. The first phase of the eastern branch opened on 11 December 2011. Construction of its second phase was initially expected to start in 2014 but still has no funding.

Quick Facts Overview, Status ...

If completed, LGV Rhin-Rhône would have three branches:

The construction of the latter two branches and of the second phase of the Eastern branch is currently unfunded.

Running north–south, the Southern branch line would help connect Germany, the north of Switzerland, and eastern France on the one hand with the valleys of the Saône, Rhône, the Mediterranean arc and finally Catalonia on the other. The east–west Eastern and Western branches lines would help connect on the one hand London, Brussels, Lille and Île-de-France (i.e., Paris and surroundings) with Burgundy, Franche-Comté, south Alsace, southern Baden, and Switzerland on the other.

A connection will be built at Perrigny, south of Dijon, to serve TGV and freight trains. Besançon Franche-Comté TGV station, located in Les Auxons will be connected to Besançon-Viotte station by a railway line which could be also used for commuter trains.

It is projected that 12 million passengers per year will use the LGV Rhine-Rhône service.[2]

Western branch

The western branch consists of the crossing of Dijon, where a new station is to be built, the connection to the Paris-Marseille line near Montbard and the connection with the LGV Sud-Est at the Pasilly-Aisy junction. This branch will speed up connections with the Île-de-France region.

Southern branch

In 2009, the regional planning procedure for the 150 km (93 mi) long south branch was launched. Seven routes have been put up for discussion by the developer Réseau ferré de France, who favours a route parallel to the A 39 motorway, at an estimated cost of €3 billion.

History

LGV Rhin-Rhône schema
Inaugural train with President Nicolas Sarkozy on board on the first stretch of the LGV Rhin-Rhône, 8 September 2011, near Genlis

The first phase of the eastern branch runs 140 km (87 mi) of the 190 km (120 mi) planned length, connecting Villers-les-Pots (east of Dijon) to Petit-Croix (southeast of Belfort), was officially opened by President Nicolas Sarkozy on 8 September 2011,[2] with passenger services starting on 11 December 2011.[3]

The eastern branch is used by TGV trains operated by SNCF. It will become a key link in both the north–south and east–west transport corridors. The line carries regional, national, and intra-European traffic. Mulhouse provides connection to Basel, Switzerland, and then to southwestern Germany and north-western Switzerland.

Finance

The financing agreement for the first phase of the eastern branch was signed on 28 February 2006. The estimated cost of the first section of the eastern branch is 2.312 billion euros, shared between many organisations.[4]

The largest contributors of funds are the Government of France (€751 million), the maintainer of the French rail network RFF (€642 million) and the European Union (€200 million).[2] Significant funding also came from the three regions of France that the line travels through: Franche-Comté (€316 million), Alsace (€206 million) and Burgundy (€131 million). A further €66 million was funded by the Government of Switzerland.[2]

Construction

Map of France showing LGVs. LGV Rhin-Rhône is shown in shades of blue, south-east of Paris.

Preparatory works began in 2005, and construction officially started on 3 July 2006 with a ceremony in Les Magny, Haute-Saône. Actual construction of the first section started north of Besançon on 7 August 2006.

Réseau Ferré de France appointed French engineering and consulting companies Setec and Egis to build the line. The construction of the Eastern branch was divided into two sections :

Journey times

Upon completion of the first section of the eastern branch, best journey time are:[6]

More information from, to ...

See also


References