LYNX_Red_Line

I-77 Bus Rapid Transit

I-77 Bus Rapid Transit

Add article description


The I-77 Bus Rapid Transit is a proposed bus rapid transit (BRT) service, connecting the towns in northern Mecklenburg and southern Iredell counties to Uptown Charlotte, North Carolina. The BRT replaces the previously planned commuter rail service, the Lynx Red Line, that was routed along the existing Norfolk Southern O-Line right-of-way. However, several issues had arisen that included ineligibility for federal funding and Norfolk Southern refusal to allow access to its right-of-way. In 2019, after a reevaluation of the entire corridor, the Charlotte Area Transit System (CATS) decided to move forward with BRT and shelve the commuter rail; which had been met with frustration by various city leaders and residents impacted by it.[3]

Quick Facts I-77 Bus Rapid Transit (Formerly Lynx Red Line), Overview ...

Since February 3, 2020, MetroRAPID, a rebranding and overhauling of four existing express bus routes, has been setup to utilize the I-77 express lanes, which were completed in 2019.[4]

The Bus Rapid Transit service is projected to begin operations in 2029.[1]

History

Commuter Rail

More information Red Line ...

The Red Line was a planned ten station commuter rail that was to connect between Mount Mourne in southern Iredell County and the proposed Gateway Station in Uptown Charlotte.[5][6][7] It would primarily serve the towns of Huntersville, Cornelius, and Davidson in northern Mecklenburg County.

It would be routed along the existing Norfolk Southern O Line right-of-way, roughly paralleling North Graham Street and North Carolina Highway 115, as it extends through north Mecklenburg County, and was estimated to be 25 miles (40 km) in length. Originally, it was thought to cost $261 million to complete the first phase by 2012 and an additional $112 million to complete phase two by 2019; the line would contain 1,200 parking spaces and 10 stations along the corridor. However, several issues have arisen that have increased the project's price tag,[8][9]

Design and planning

By 2011, the Lynx Red Line was planned to be built in one phase. Due to less revenue in the transit tax, in January the Metropolitan Transit Commission voted that the Lynx Red Line along with the Blue Line extension were the top two priorities, leaving the streetcar to be funded by the city and postponing further work on the LYNX Silver Line and the Airport corridor until after the Red Line and Blue line projects were completed. The Red Line was projected to be in operation by mid to late 2018.

Feasibility

By June 2011 the project had been 90% designed and an operating agreement was signed with Norfolk Southern Railway, but the project lacked nearly 80% of the needed funds to begin construction. In October 2012, The Charlotte Observer noted that "the Red Line...has little chance of federal funding, and CATS may not have enough money to pay for even a portion of construction costs. The NCDOT is working on creative ways to finance the project, but it appears to be years away."[10]

On October 17, 2012, the NCDOT, the Red Line Task Force and CATS requested Norfolk Southern to conduct a study of the "Red Line" concept. As the Red Line would utilize the NS O-Line between Charlotte and Mooresville, the study would determine if and how both freight and passenger services could use the same line while allowing normal freight services to continue. It was estimated at a meeting of the task force on October 24 that the study would be initiated by late January 2013 and completed by early 2014, after which further feasibility studies and projections could be made.[11] However, in early 2013, Norfolk Southern expressed its doubts that the $416 million project would be feasible.[12]

On June 25, 2014, following the completion and release of the feasibility study, CATS officials said that the Red Line would be too costly and complicated to build.[8] Several reasons were provided, including:

  • The continued refusal of Norfolk Southern to share its existing trackage with CATS, necessitating the construction of a new railway line parallel to the NS rails. This would increase the overall project cost by $215 million and cause "multiple disruptions to adjacent communities", as building a parallel rail line would involve construction costs, right-of-way purchases, and the complete rebuilding of all road intersections along the proposed line.
  • The project's ineligibility for federal funding due to low ridership projections.
  • The inability of CATS to fund the Red Line on its own.

Despite the negative assessments of the feasibility study, the Metropolitan Transit Commission, including the Red Line task force, did not take any official steps to disband the project. While the director of the N.C. DOT rail division, Paul Worley, said that he would work with Norfolk Southern officials to begin a study concerning the proposed Gateway Station, he said that the Red Line concept would not be included, as "no viable plan" for it now existed. Though the mayor of Davidson, John Woods, said the results of the feasibility study were "a serious setback," he added that developing transit in the northern portion of Mecklenburg County remained important for the region, and one possible alternative to a commuter rail line could be bus rapid transit.[9]

Charlotte city officials have continued to maintain a strong interest in the original Red Line project.[13] In June 2021, Charlotte city manager Marcus Jones said the Red Line remained the city's "top priority" within the overall regional transit plan.[13] A financial consulting firm has advised the Charlotte city council that the Red Line as originally planned could begin operating in 2031, and could be built for $674 million.[1][14] Municipal leaders in North Mecklenburg communities, however, including Cornelius mayor Jeff Tarte, oppose future transit taxes and projects led by Charlotte officials, are skeptical Norfolk Southern will change its stance on sharing its lines with a commuter rail, and have doubted the long-term viability of diesel-powered locomotive technology.[13]

North Corridor reevaluation

In July 2018, CATS began a reevaluation of the Red Line and three alternative options to replace it if still not feasible. The process involved a series of public meetings and various surveys to know where the public stands regarding the Red Line and how each of the alternative options rank.[15][16] After conducting a survey to elicit public opinion on the LYNX Red Line,[17][18] CATS announced in January 2019 that plans for either a commuter or light rail between Uptown and Mooresville were not feasible. In the short term, CATS will run express buses along the I-77 Express lanes. Service would be expanded to true bus rapid transit (BRT) by 2029, when the service is projected to begin.[1][19][20]


References

  1. Kuznitz, Alison (June 28, 2021). "The price tag just increased for Charlotte's big transportation plan. Here's the latest". Charlotte Observer. Retrieved July 3, 2021.
  2. Boraks, David (January 13, 2020). "CATS Changing North Meck Express Bus Routes To Use I-77 Toll Lanes". Charlotte, NC: WFAE. Retrieved March 29, 2020.
  3. "2030 Transit Corridor System Plan". Charlotte Area Transit System. Retrieved September 6, 2014.
  4. "Red Line Project". Charlotte Area Transit System. Retrieved September 6, 2014.
  5. "Home". Red Line Regional Rail. Archived from the original on September 6, 2014. Retrieved September 6, 2014.
  6. "Major blow dealt to CATS Red Line project". Charlotte, NC: WCNC-TV. June 27, 2014. Retrieved September 6, 2014.
  7. Harrison, Steve (June 26, 2014). "Charlotte commuter train price jumps by $215M". The Charlotte Observer. Retrieved September 6, 2014.
  8. "Leaders: Charlotte area can't pay for transit needs". The Charlotte Observer. April 12, 2013. Archived from the original on June 28, 2013. Retrieved April 28, 2013.
  9. Kuznitz, Alison (July 2, 2021). "These are the 4 biggest obstacles facing the Red Line transit plan in Mecklenburg". Charlotte Observer. Retrieved July 3, 2021.
  10. Bruno, Joe (28 June 2021). "Cost increased and timeline pushed back for light rail expansion in Charlotte". WSOC-TV 9. Retrieved 29 June 2021.
  11. Hughes, Rob (July 17, 2018). "CATS to survey public on Red Line that would connect Lake Norman to uptown". Charlotte, NC: WCNC-TV. Retrieved July 18, 2018.
  12. "North Corridor Init Screening Brochure" (PDF). Charlotte Area Transit System. July 16, 2018. Retrieved July 18, 2018.
  13. Harrison, Steve (January 23, 2019). "CATS Gives New Details On 2030 Plan, Including New Rail Along I-277". Charlotte, NC: WFAE. Retrieved January 23, 2019.

Share this article:

This article uses material from the Wikipedia article LYNX_Red_Line, and is written by contributors. Text is available under a CC BY-SA 4.0 International License; additional terms may apply. Images, videos and audio are available under their respective licenses.