Boten–Vientiane railway

Boten–Vientiane railway

Railway line in Laos


The Boten–Vientiane railway is the Lao section of the Laos–China Railway (LCR), running between the capital Vientiane and the northern town of Boten on the border with Yunnan, China. The line was officially opened on 3 December 2021.[9]

Quick Facts Overview, Other name(s) ...
Vientiane train station
Inside the railway station at Vientiane
Luang Prabang Station

A collaborative project between Laos and China, the line's northern end is directly connected to the Chinese rail system at Mohan in Yunnan, through the Yuxi–Mohan railway, and has provisions in the south to link up with the Bangkok–Nong Khai high-speed railway in Thailand and possibly all the way to Singapore via HSR. The railway ends at Vientiane South cargo station. The Boten–Vientiane railway is an integral section of the central line on the Kunming–Singapore railway,[10] and was constructed as part of the Belt and Road Initiative (BRI).[11][12]

History

Planning

Laos is the only landlocked country in Southeast Asia, which burdens it with a competitive disadvantage in trade.[13] During French rule, the French failed to develop a plan to build railways in Laos, with only the 7 km (4.3 mi) Don Det–Don Khon railway being completed.[14] A railway link from China through Laos would greatly reduce cargo transit times and transportation costs between the two countries.[13]

The first talks about the railway linking Laos and China began in 2001. A Lao politician of Chinese descent, Somsavat Lengsavad, was reportedly the driving force behind the project on the Laotian side. In October 2010, plans were announced for a 530 kilometres (330 mi) standard gauge railway linking Vientiane to Xishuangbanna, in Yunnan province in China.[15][16] Construction was expected to begin in 2011, for completion in 2014.[17][18] There are plans to extend this railway south, from Vientiane across the Thai border to Bangkok.[19]

The project initially stalled in the wake of the 2011 corruption scandal involving China's minister of railways, Liu Zhijun, but negotiations continued. In November 2012, the Laotian press reported that the money for the construction of the railway would be borrowed from the Export–Import Bank of China,[20] and construction would be started in 2013 and completed in 2018.[15] By 2015, a revised plan was agreed upon, under which both countries would jointly finance and operate the railway with a build-operate-transfer arrangement.[21] Construction work worth US$1.2 billion was awarded to the China Railway Group in September 2015.[21]

Construction and completion

Viaduct under construction near Vientiane
Bridge construction in Luang Prabang Province

Construction began at Luang Prabang on 25 December 2016.[22] At the end of 2017, the construction phase was 20% completed,[23] and in September 2019 progress was reported as 80% completed.[24] Unexploded bombs that have been dropped during the Vietnam War would also be removed along the route.[25]

As of June 2020, Chinese state media reported that the US$6 billion project was 90% complete. Work crews started laying track in Laos in March 2020, five years after breaking ground. With all of the hundreds of tunnels, bridges and viaducts completed, cargo service was scheduled to start from December 2021.[26] In April 2021, the northernmost section in Luang Namtha Province was 97% complete. Track laying of the last section in Oudomxay Province would be completed in May, leaving the project well on track for a 2021 opening.[27] Track-laying was officially completed on 12 October 2021.[7] The first EMU was delivered to Vientiane on 16 October 2021, and the line opened on 3 December 2021, a day after the 46th anniversary of the Lao PDR.[9][6]

The railway is expected to boost tourism, with passenger traffic to account for the majority of traffic on the line.[12][28] The Thai province of Nong Khai is also expected to gain more visitors through the railway, as well as fruit exports from Thailand to China benefiting from reduced transportation costs.[29]

As of 2024, it is the most significant Belt and Road Initiative project in Laos.[30]:212

Future expansion

Since the line uses a different rail gauge from the existing Thai Northeastern Line link from Bangkok to Thanaleng, running into Thailand is not yet possible for passenger trains. A branch to Thanaleng Dry Port freight yard was completed in July 2022, allowing transfer of cargo between Thai metre gauge railway and Laos standard gauge railway.

However, the Vientiane end of the line will eventually cross the Mekong River on a new bridge to meet up with the Bangkok–Nong Khai high-speed railway once it is completed, making the connection.[31] As of 2023, the design of this extension is in progress with a target completion date of 2028.[32]

Financing

The cost of the project is estimated at US$5.965 billion[33] or RMB 37.425 billion.[34] The railway is 60% funded with debt financing ($3.6 billion) from the Export–Import Bank of China, and the remaining 40% ($2.4 billion) by a joint venture company between the two countries, in which China holds a 70% stake. Of the remaining 30%, the Laotian government disburses $250 million from its national budget and borrows $480 million further from the Export–Import Bank of China.[35] It is the most expensive and largest project to be constructed in Laos as of 2021.[36]

The cost of the railway has contributed to a US$480 million increase in Lao debt to the Export–Import Bank of China. Western publications subsequently claimed that Laos could end up falling into a default on its debts.[37][35][38] In 2019, the Australian think-tank Lowy Institute estimated Laos' debt to China at 45% of its GDP.[37] In 2020, American credit agency Fitch Ratings assigned Laos a 'CCC' credit rating, stating that the country has "excessive debt".[36]

Ridership

Between January 2021 and December 2021, the Laos–China Railway as a whole transported over 1 million passengers and 500,000 tonnes of cargo, according to the transport authorities of Yunnan Province.[39]

Infrastructure

47% of the railway is spanned over 75 tunnels and 15% is set on viaducts spread over 167 bridges.[21][22] Vientiane railway station, the largest station on the railway, is situated in Xay Village in Xaythany District and consists of four platforms with seven track lines and two additional platforms with three lines reserved; it is expected to connect with other railway lines planned for Laos. The station can accommodate up to 2,500 passengers with a total area of 14,543 square metres.[40]

The railway is built on a single track with passing loops and is electrified to China's Class I trunk railway standards, suitable for 160 km/h (100 mph) passenger and 120 km/h (75 mph) freight trains, making Laos the first country to connect to the Chinese high-speed railway network using Chinese technology.[28]

Rolling stock

A high-speed train carriage, with bilingual signage in Laotian and Chinese

Passenger services employ CR200J trainsets, and for freight hauling, HXD3CA locomotives are used.[41][42][43]

Cargo

On 4 December 2021, a day after opening the China–Laos railway, the Vientiane Logistics Park, one of a total of nine logistics centres in Laos, was officially opened by Prime Minister Phankham Viphavanh at Thanaleng.[44]

List of stations

32 stations are planned along the line,[45] of which 21 stations were initially constructed, including 10 passenger stations and 11 cargo stations:[46][47][48]

More information Station name, Station type ...

Controversies

Radio Free Asia reported in October 2021 that some Lao villagers displaced from their land by the line's construction complained that they had still not received compensation.[50]

In the first year of operation, the railway only allowed ticket purchases up to three days in advance and online sales were not available. That resulted in extremely long lines at ticket offices, and express trains often sold out the day ticket sales opened.[51] This has since been partially ameliorated with the LCR mobile app, which allows online purchase of tickets; albeit only for users with a Laotian phone number and still only for three days in advance.

See also


References

  1. "China and Laos open $6 billion high-speed rail link". Reuters. 2021-12-03. Retrieved 2021-12-06.
  2. "中老铁路12月3日全线开通运营 昆明至万象约10小时可达". 荆楚网. 2021-12-02. 中老铁路开通初期,老挝段由老中铁路公司委托中国铁路昆明局集团公司运营维护
  3. "一季度中老铁路客货两旺". CRI online. 17 April 2023. Retrieved 17 April 2023.
  4. "Nong Khai plans for rail link with China". Bangkok Post. Retrieved 17 September 2021.
  5. 齐磊. "中老铁路全线铺轨完成 年内开通运营". cn.chinadaily.com.cn. Retrieved 2021-10-20.
  6. "How Laos is overcoming landlockedness and bolstering growth". East Asia Forum. 2021-03-05. Retrieved 2021-05-02.
  7. Freeman, Nick (2019-12-11). "Laos' high-speed railway coming round the bend". ThinkChina - Big reads, Opinion & Columns on China. Retrieved 2020-11-05.
  8. "NEW CHINA-LAOS LINK". Railways Africa. Retrieved 2010-11-09.
  9. "LAOS LINK WITH CHINA". Railways Africa. 2010-12-12. Retrieved 2010-12-12.
  10. "Everything You Need to Know About the Laos–China Railway". The Laotian Times. 20 February 2017. Retrieved 2018-12-20.
  11. "Nearly 80 pct of China–Laos railway construction completed". Xinhua News Agency. 22 September 2019. Archived from the original on September 24, 2019. Retrieved 2020-01-31.
  12. "ການກໍ່ສ້າງພື້ນຖານໂຄງສ້າງທາງລົດໄຟ ລາວ-ຈີນ ໄລຍະທາງຜ່ານແຂວງຫຼວງນ້ຳທາ ສຳເລັດແລ້ວ 97%" [Construction of Lao-China Railway Infrastructure via Luang Namtha Province Completed 97%]. Target Magazine (in Lao). Archived from the original on 2021-05-04. Retrieved 2021-05-04.
  13. Brian King (22 August 2017). "Chinese railway could put Laos on the tourist map". CNN. Retrieved 2020-11-05.
  14. "Laos' China-backed railway: hopes in Thailand, fears in Luang Prabang". South China Morning Post. 2021-08-10. Retrieved 2021-08-12.
  15. Gerstl, Alfred (2023). "China in its Immediate Neighborhood". In Kironska, Kristina; Turscanyi, Richard Q. (eds.). Contemporary China: a New Superpower?. Routledge. ISBN 978-1-03-239508-1.
  16. Phonevilay, Latsamy (4 July 2020). "Construction of Vientiane Station Commences on Laos–China Railway". The Laotian Times. Retrieved 6 July 2020.
  17. "Công ty Đường sắt Lào Trung mua hai đoàn tàu CR200J của Trung Quốc". tapchilaoviet.org (in Vietnamese). 29 September 2020. Retrieved 2 July 2021.
  18. "老挝北部的中老铁路建设如火如荼-新华网". 28 March 2018. Archived from the original on March 31, 2018.
  19. "中老铁路-新建铁路磨丁至万象线四电工程施工总价承包中标结果". 18 December 2019. Archived from the original on 5 October 2022. Retrieved 11 June 2021.
  20. Syboun, Khonephachanh (13 January 2022). "Laos-China Railway Allows Three-Day Advance Ticket Purchases". Retrieved 18 April 2023.

Share this article:

This article uses material from the Wikipedia article Boten–Vientiane_railway, and is written by contributors. Text is available under a CC BY-SA 4.0 International License; additional terms may apply. Images, videos and audio are available under their respective licenses.