List_of_offshore_wind_farms_in_the_Netherlands

Wind power in the Netherlands

Wind power in the Netherlands

Add article description


As of November 2023, wind power in the Netherlands has an installed capacity of 11,602 MW, 40.9% of which is based offshore.[1] In 2022, the wind turbines provided the country with 18.37% of its electricity demand during the year.[2] Windmills have historically played a major part in the Netherlands by providing an alternative to water driven mills.[3]

Aerial view of Windpark Krammer

In March 2022, the Dutch government announced that by 2030 offshore wind was to become the Netherlands' biggest power source, aiming at 21 GW of installed capacity.[4]

Since 2015 there has been a trend towards the deployment and planning for large wind farms, both onshore and offshore, with a view to the approximate tripling wind power capacity from 2015 levels by 2023.[5] The first of these, the 429 MW Noordoostpolder wind farm was already partially deployed by year end 2015 whilst the 600 MW Gemini offshore wind farm was commissioned in 2017. These newer and larger wind farms are making use of some of the largest wind turbines available, in particular in the case of Noordoostpolder the Enercon E-126 7500 kW wind turbine, the largest onshore turbine available at that time. The Netherlands is also well prepared for a significant rise in the production of intermittent power from wind energy by good linkages to its neighbours via high voltage cables enabling power to be imported or exported as required. These include the 580 km NorNed submarine cable (700 MW) link to Norway, the 1,000 MW BritNed cable link to the United Kingdom and the COBRA cable link to Denmark (700 MW).

Many of the numerous smaller and older wind farms in the Netherlands consist of much smaller turbines compared to those typically deployed today. These were often manufactured by lesser known wind turbine manufacturers, sometimes producing innovative products such as the Nedwind 2 blade turbine. Many of these smaller companies were eventually acquired by the larger wind turbine manufactures such as Vestas, Siemens and Lagerwey.

Installed capacity

  Cumulative sea-based wind capacity (MW)
  Cumulative land-based wind capacity (MW)
Installed land-based wind capacity (MW) by province in 2022[6]
More information Year, Installed capacity (MW) ...

Future targets

The Dutch government has set a target of 6,000 MW nameplate capacity of onshore wind power by 2020 and 4,450 MW of offshore wind power by 2023, neither of which were met.[5] This will contribute towards the Dutch target of 14% renewable energy use out of total energy use by 2020[9] and 16% by 2023.[5] In 2020 wind power provided 11.54% of Dutch electricity generation (see table above) while solar power provided an additional 7.25%, for a combined 18.79%

For offshore wind a new system of tendering is under development. New wind farm deployment is based on the SER agreement that describes a plan for five years of tendering 700 MW per year. Under this system the government chooses locations and organizes tenders for projects of 350 MW, and project developers can offer bids for each farm. These sites are also surveyed centrally by the government, allowing developers to avoid costly and multiple surveys.[10]

More information Call for tender (year), Capacity (MW) ...

Turbine manufacturers and repowering

Many small scale wind farms exist throughout the Netherlands which bear testament to earlier models of wind turbines and lesser known manufacturers which provided a range of niche products, ranging in size and power output. There are several Dutch turbine manufacturers that continue to manufacture both large and small installations for domestic and international clients. Smaller turbines are often used for off grid, bespoke and community power internationally.

More information Manufacturer/ Model, Notes ...

Some of the newer larger wind farms currently under construction are replacing smaller turbines previously installed at given locations. One such example is the largest wind farm in the Netherlands, Noordoostpolder, which is installing industrial scale wind turbines such as the new Enercon onshore wind turbines, at the time the largest onshore turbines in the world rated at 7500 kW nameplate capacity. The turbines have a hub height of 135 metres (443 ft) and each new turbine can generate as much electricity as all 50 turbines of the old wind farm combined.[12] The wind farm demonstrates the growth in scale in wind power as between 1987 and 1991 it was the largest of its kind in Europe with 50 turbines and a total nameplate capacity of 15 MW. The new Zuidwester site at the wind farm will have just 12 turbines and a total nameplate capacity of 90 MW.[13] A second hand market for turbines also exists, which could grow as older turbines are replaced by larger newer ones.[14]

Timeline of developments

2022

In February 2022 the Netherlands announced it increased its offshore wind target to 21 GW by 2030. That would meet approximately 75% of the countries electricity needs. With this, offshore wind energy makes an important contribution to achieving the increased climate target of 55% less CO2-emissions.[15]

2018

In March 2018 the Dutch government announced that it will build between 2023 and 2030 several new windfarms with a total installed capacity of 7 gigawatt.[16] Where the parks will come and how they will be built is still being discussed. However, the government wants 40% of the total electricity used in 2030 in the Netherlands to be supplied by wind.[17]

2016

In the first week of December 2016, all 150 turbines of the new 600 MW Gemini offshore windfarm began producing power, and the project is expected to be fully commissioned by mid 2017.[18] In July 2016, the first two stages of offshore wind farm development for a combined 700 MegaWatt capacity in a water area near Borssele was awarded to DONG Energy at a price of 7.27 Euro cent per kilowatt hour for 15 years. Transmission costs of 1.4 eurocent/kWh is to be added as TenneT is required to take power from sea to shore.[19] [20] [21]

2015 2015 was a record year for new installations in the Netherlands with 586 MW added of which 180 MW were offshore. This record was immediately beaten the following year with another 766 MW being added.[1]

The Dutch government has expressed the aspiration to build 4.450 MW of offshore wind power by 2023[5] which will have a considerable impact on the Dutch electricity grid, operated by TenneT. [22] As a first step, the government has determined 65 sites for offshore wind farms in the North Sea and IJsselmeer. [23]

2013

By December 2013, 1,975 wind turbines were operational on land in the Netherlands, with an aggregate capacity of 2,479 MW.[24] An additional 228 MW of capacity was installed at sea.[25]

2011

In November 2011, the Dutch government decided to no longer fund €6 billion per year to maintain subsidized wind kWh at €0.18. It sharply cut subsidies down to €1.5 billion, leaving private sector to carry over wind turbine investments should these be beneficial.[26]

Onshore wind power

Whilst there are a growing number of large onshore wind farms in the Netherlands, most of the onshore farms in 2015 consisted of a large number of small wind farms, including many single installation turbines as well as farms of between 1–10 turbines. In total there were 3,004 MW of onshore wind power at the end of 2015. Most wind power is produced in the province of Flevoland.[24] A few of the larger wind farms are listed here.

More information Province, Capacity (MW) ...

Noordoostpolder

The largest wind farm in the Netherlands is Noordoostpolder with a capacity of 429 MW. The farm consists of three smaller wind farms owned by separate organisations with local community links. The wind farm's 86 wind turbines will produce 1.4 billion kWh of electricity, enough. power for over 400,000 households every day, a figure roughly equivalent to the number of households in the Northern Netherlands.[12]

Westereems

Wind turbines at the Westereems Wind Park

The next largest onshore wind farm is the Westereems wind farm located in Eemshaven in Groningen, in the north of the Netherlands.

Princess Alexia

Up until the Westereems Wind Park was commissioned the largest onshore wind farm was the Princess Alexia Windpark in Zeewolde (122MW),[44] consisting of 36 REpower turbines and a 3.2MW/33MWh battery storage power station of BMW i3 batteries.[45]

Eemmeerdijk

The Eemmeerdijk wind farm consists of wind turbines with just 2 blades, manufactured by Nedwind. The 19 turbines have a combined nominal power of 18 MW.[37] The wind farm was built in 1998.

In 2006 the tower of one of the turbines had buckled. The damaged wind turbine could be safely dismantled.[46] A second wind turbine was also dismantled. In January 2023 another wind turbine collapsed due to strong winds, leaving the farm with only 16 turbines.[47]

Offshore wind power

Current offshore wind farms

More information Nameplate capacity (MW), Turbines ...
Offshore wind farm locations (interactive map)

Future offshore wind farms

More information Capacity (MW), Tender ...

Offshore grid

Early offshore wind farms were responsible for installing their own offshore grid infrastructure to connect their wind farm to the main electricity grid. From 2016 onwards, the national grid operator TenneT has been designated as the offshore grid operator and is responsible for the construction of transmission infrastructure at sea.

Wind farms are connected via standardised connections of 700 megawatts (MW) AC or 2 gigawatts (GW) HVDC for larger wind farms located further offshore. Through the standardisation of these offshore platforms, the government hopes to significantly reduce the overall development, construction and maintenance costs.[74][75]

Luchterduinen

Princess Amalia Wind Farm in the North Sea

The Eneco Luchterduinen wind farm was officially opened in September 2015 and is a 50/50 joint venture between Dutch energy company Eneco and Japan's Mitsubishi corporation. The 129 MW Eneco Luchterduinen wind farm is located 23 km off the coast between Zandvoort and Noordwijk cities in the Netherlands. The farm consists of 43 Vestas V112 turbines of 3 MW capacity each.[76]

Princess Amalia

In 2008, a second, somewhat larger offshore wind farm was built: the Princess Amalia Wind Farm, consisting of 60 Vestas V80 2MW turbines totaling 120 MW, sufficient to power 125,000 homes and help the Netherlands cut 225,000 tonnes of carbon dioxide emissions.[77] [78] The wind park was developed off the coast of IJmuiden by Econcern and Eneco Energie, at a total cost of $522.3 million.[79]

Egmond aan Zee (OWEZ)

In 2006, the Egmond aan Zee Offshore Wind Farm was built, consisting of 36 Vestas V90 3MW turbines, totaling 108 MW, sufficient to light 100,000 houses.[80] [81] [82] The project cost $272 million and is cooperatively owned by Royal Dutch Shell and the Dutch utility company Nuon.

Lely

Lely Offshore Wind Farm

Lely was the first offshore wind farm in the Netherlands. Construction began in 1992 and the farm was completed in 1994. The nearshore wind farm had 4 Nedwind 500 KW turbines located 1 km to shore.

In 2014 one of the turbines lost its rotor with both blades due to metal fatigue.[83] The 4 wind turbines were eventually dismantled in 2016, after 22 years of service.[84]

See also

Notes

  1. Calculated value from total installed nameplate capacity and actual electricity generation. Statistical artifacts possible if new capacity was added late in the year

References

  1. "WindStats". Bosch and van Rijn. Retrieved 22 November 2023.
  2. "Renewable electricity; production and capacity". opendata.cbs.nl (in Dutch). Retrieved 5 June 2023.
  3. Blunt, Elizabeth. "Exploiting wind power in Holland." BBC News. N.p., 13 November 2000. Web. 14 October 2009. <http://news.bbc.co.uk/2/hi/europe/1021714.stm>.
  4. "Statistieken". windstats.nl. Retrieved 3 January 2023.
  5. Diest, Erik Van (20 January 2021). "Windenergie maakt forse inhaalslag in 2020". NWEA (in Dutch). Retrieved 24 February 2021.
  6. "Sun and Wind Energy". 9 November 2015.
  7. "Drie nieuwe windparken in de Noordzee". nos.nl (in Dutch). 27 March 2018. Retrieved 1 April 2018.
  8. "Windenergie op zee". rijksoverheid.nl (in Dutch). 11 August 2016. Retrieved 1 April 2018.
  9. 4C Offshore, Key project dates for Gemini [2], accessed 22 January 2017
  10. Offshore Wind Power Research, WE@Sea, accessed December 28th 2009. [verification needed]
  11. "Offshore wind farm opens off the coast of the Netherlands". The New York Times. 18 April 2007. Retrieved 14 October 2009. [verification needed]
  12. Hudson, Alexandra. "Dutch build towering wind turbines out at sea." Reuters. [verification needed]
  13. "Werken aan een nieuwe toekomst met windenergie". Windkoepel (in Dutch). Retrieved 2 March 2021.
  14. "Feiten & cijfers". Windpark Noordoostpolder (in Dutch). Retrieved 24 February 2021.
  15. "Home". Windpark Wieringermeer (in Dutch). Retrieved 25 February 2021.
  16. "Home". Windplanblauw (in Dutch). Retrieved 2 March 2021.
  17. "Windpark Zeewolde – Windpark Zeewolde". windparkzeewolde.nl. Retrieved 2 March 2021.
  18. "Windpark De Drentse Monden en Oostermoer - Home". De Drentse Monden en Oostermoer (in Dutch). Retrieved 25 February 2021.
  19. RWE. "Windpark Westereems". www.group.rwe (in Dutch). Retrieved 24 February 2021.
  20. "Windpark N33". www.windparkn33.nl. Retrieved 24 February 2021.
  21. Eneco. "Windpark Maasvlakte 2". Windpark Maasvlakte 2 (in Dutch). Retrieved 22 February 2022.
  22. "Eneco en Vattenfall openen Windpark Slufterdam 2.0 met dubbel zoveel vermogen". Haven van Rotterdam (in Dutch). 12 February 2019. Retrieved 25 February 2021.
  23. "Windpark Deil – Duurzame voorsprong in Deil" (in Dutch). Retrieved 24 February 2021.
  24. "Windpark Nij Hiddum-Houw". Nij Hiddum-Houw (in Dutch). Retrieved 3 March 2023.
  25. "BMW drives Vattenfall storage". 14 March 2017. Retrieved 14 March 2017.
  26. "Knak in windmolen 'wereldwijd eerste'". De Stentor (in Dutch). 13 February 2006. Retrieved 10 November 2023.
  27. Lankhorst, Sabine (4 January 2023). "Eemmeerdijk Wind Farm turbine collapses". Windpowernl. Retrieved 11 April 2023.
  28. NoordzeeWind (Egmond aan Zee)
  29. "Shell NoordzeeWind". www.shell.nl (in Dutch). Retrieved 2 April 2023.
  30. OWEZ (Netherlands) offshore wind farm 4C . Retrieved: 24 August 2010.
  31. Princess Amalia (Netherlands) offshore wind farm 4C . Retrieved: 24 August 2010.
  32. Borssele 1 & 2 generates first power. Retrieved: 1. August 2020.
  33. "Homepage". Blauwwind (in Dutch). Retrieved 23 February 2021.
  34. "Vattenfall Hollandse Kust - Windpark op de Noordzee". Windpark Hollandse Kust Zuid (in Dutch). Retrieved 23 February 2021.
  35. "Homepage". Crosswind Hollandse Kust Noord (in Dutch). Retrieved 23 February 2021.
  36. "Wind energy in Europe in 2019 - Trends and statistics". WindEurope. Retrieved 12 October 2020.
  37. Lely (Netherlands) offshore wind farm 4C . Retrieved: 24 August 2010.
  38. "Irene Vorrink: a nearshore wind farm". Vattenfall Power Plants. Retrieved 28 February 2022.
  39. "Nearshore Wind Farm to Be Dismantled". Offshore Wind. 8 March 2022.
  40. "Feiten, cijfers en planning – Westermeerwind" (in Dutch). Retrieved 23 February 2021.
  41. "Homepage". Windpark Fryslân (Dutch). Retrieved 27 March 2017.
  42. "Waar komt het windpark?". Windplanblauw (in Dutch). Retrieved 4 April 2021.
  43. Zaken, Ministerie van Algemene (10 June 2022). "Planning en voorgenomen tenderschema windenergie op zee - Publicatie - Rijksoverheid.nl". www.rijksoverheid.nl (in Dutch). Retrieved 15 June 2022.
  44. "Offshore Grid". Noordzeeloket UK. Retrieved 17 March 2023.
  45. "Offshore projects Netherlands". TenneT. Retrieved 17 March 2023.
  46. "Power Technology.com". Power Technology.
  47. Hudson, Alexandra. "Dutch build towering wind turbines out at sea." Reuters. [verification needed]
  48. Hudson, Alexandra. "Dutch build towering wind turbines out at sea." Reuters. [verification needed]
  49. "Offshore wind farm opens off the coast of the Netherlands". The New York Times. 18 April 2007. Retrieved 14 October 2009. [verification needed]
  50. The Select Committee for Energy Independence and Global Warming. "In the sea, the Netherlands finds threats, hope." The Select Committee for Energy Independence and Global Warming. N.p., n.d. Web. 14 Oct.Q7 doesn't exist 2009.<http://globalwarming.house.gov/impactzones/netherlands>. [verification needed]
  51. annevisser (30 December 2014). "Lely Shut Down as Nuon Investigates Turbine Malfunction". Offshore Wind. Retrieved 11 April 2023.
  52. "offshoreWIND.biz". 28 September 2016.

Share this article:

This article uses material from the Wikipedia article List_of_offshore_wind_farms_in_the_Netherlands, and is written by contributors. Text is available under a CC BY-SA 4.0 International License; additional terms may apply. Images, videos and audio are available under their respective licenses.